| Entity | M/s Print & Packers Flexipack (Partnership Firm) |
| PAN | ABDFP4532C |
| Location | B-4(P), Mega Industrial Park, Bihta, Patna – 801103, Bihar |
| Products | Auto Corrugated Boxes + Multi-Layer Blown Film + Rotogravure Printing & Lamination |
| Installed Capacity | 17,520 MTPA (Corr: 14,400 MT | Film: 1,920 MT | Print Lam: 1,200 MT) |
| Total Project Cost | ₹41.46 Crore |
| Construction | COMPLETE — Factory building fully constructed |
| Machinery | INSTALLED — All plant & machinery installed and ready |
| Power | 11 KV HT Connected (100 KVA active) |
| Power Upgrade | April 2026 — 500 KVA (cost already budgeted) |
| Commercial Production | 1st Week of May 2026 |
| Lending Bank | Punjab National Bank, Boring Road, Patna |
| TEV Report | Resurgent India Ltd — June 2024 (TEV-2024/2025-16583) |
Plant & Machinery Breakdown
Total P&M: ₹24.53 Cr + Civil: ₹7.70 Cr + Electrical/Solar: ₹4.84 Cr = ₹41.46 Crore
Auto Corrugated Box Line
₹7.60 CroreCapacity: 14,400 MT/Year
- ▸Board width: 1,800mm | Speed: 120 m/min
- ▸Auto Folder Gluer with Stitching Machine
- ▸Double Color Printer Slotter + Stacker
- ▸GSM range: 80–250
3-Layer Blown Film + Rotogravure
₹12.60 CroreCapacity: 3,120 MT/Year (Film + Lamination)
- ▸3-Layer Blown Film Line (Kobra/Rajoo)
- ▸9-Color Rotogravure Printing Machine
- ▸Lamination + Slitting Machine
- ▸Air-cooled chiller + GDMS + Genset/UPS
Utilities & Support Equipment
₹2.08 CroreCapacity: Full Plant Support
- ▸Forklift (3T Diesel) + Boiler + Thermax
- ▸Thermax automatic steam system
- ▸Rotary screw air compressor
- ▸Lab equipment + erection
Electrical + Solar Infrastructure
₹4.84 CroreCapacity: Complete Power System
- ▸11 KV HT connected (active since June 2025)
- ▸500 KVA upgrade: April 2026 (cost budgeted)
- ▸500 KWP rooftop solar (Tata Power) — planned
- ▸Full electrical equipment installed
Project Cost Breakup
Land & Site₹486.73 L (11.74%)
Factory/Civil₹769.67 L (18.56%)
Plant & Machinery₹2453.24 L (59.17%)
Working Capital Margin₹220 L (5.31%)
IDC₹181.29 L (4.37%)
Pre-op Expenses₹34.93 L (0.85%)
TOTAL₹4,145.86 Lakh (100%)
| Component | ₹ Lakh | % |
|---|---|---|
| Land & Site | 486.73 | 11.74% |
| Factory/Civil | 769.67 | 18.56% |
| Plant & Machinery | 2453.24 | 59.17% |
| Working Capital Margin | 220.00 | 5.31% |
| IDC | 181.29 | 4.37% |
| Pre-op Expenses | 34.93 | 0.85% |
| TOTAL | 4,145.86 | 100% |
Power Infrastructure
CA Number
109033868
Connection Date
05 June 2025
Tariff
HTS-I (High Tension Industrial) — 11 KV
Active Consumption
11,509 KVAH/month (Jan 2026)
Energy Charges
₹92,733/month
Bihar IIP Subsidy
₹18,185/month (active)
Net Bill (Jan 2026)
₹1,19,625 (after subsidy & rebate)
Security Deposit Paid
₹4,73,771